Home / Project implementation
 
Project implementation
13.02.2015

Project Duration

The project started on 10th November 2014 and will run for 24 consecutive months.

Project Phasing

Inception Phase: 10th November 2014 - 10th January 2015

Implementation Phase: 11th January 2015 - 10th September 2016

Completion Phase:  11th September 2016 - 10th November 2016

This project is financed by European Union and implemented by a consortium of DevStat (Spain), AAM (Hungary) and the Statistical Office of the Slovak Republic (SOSR), led by GFA Consulting Group (GFA Germany).